Colocation Insights

  • The vacancy rate for colocation capacity fell to 0.24% in H1, driven by exponential demand growth.
  • Strong preleasing has made it difficult for occupiers to secure 5-to-10 MW of contiguous space in existing and planned facilities.
  • All capacity delivering in 2026 has been committed, pushing preleasing activity into 2027 and beyond.

Market Trends

  • The market delivered over 1.6 GW of capacity in 2025 and H1 2026, despite resource constraints.
  • Overall rental rates held steady in H1. However, with only 10.8 MW of available supply, asking rates for 10-plus-MW requirements rose to $160 to $185 per kW.
  • Dominion Energy's batching system continues to extend power delivery timelines for new projects, intensifying competition for entitled sites.

Notable Activity

  • Digital Realty has agreed to purchase a stake in three fully leased data centers for $3.5 billion from Blackstone-affiliated funds.
  • Amazon Web Services purchased 122 acres in Loudoun County for data center development.
  • Stack Infrastructure topped out the first of 19 planned buildings at its 1-GW campus in Stafford County.

Figure 1: Historical Market Information

Source: CBRE Research, CBRE Data Center Solutions, H1 2026.

Figure 2: Historical Supply and Demand

Source: CBRE Research, CBRE Data Center Solutions, H1 2026.

Figure 3: % of Total Primary Market Inventory

Source: CBRE Research, CBRE Data Center Solutions, H1 2026.

Figure 4: Market Fuel Mix

Source: Dominion Power.

Figure 5: Average Asking Rates

Source: CBRE Research, CBRE Data Center Solutions, H1 2026.
Several server racks, showcasing a robust IT infrastructure suitable for technology companies or data centers.
Property Type

Data Center Solutions

Our lifecycle data center service offering consolidates your data center real estate, facilities and technology systems into a single operational and financial model.