- Despite challenges, new data center projects in Metro Atlanta can be completed by 2027. This hinges on strong end-user demand, proactive planning, utility coordination and favorable permitting.
- Despite supply constraints and high absorption, the cost per kW remained relatively stable in H1 2025.
- Next-generation "neo-cloud" companies (AI, Large Language Model, High Performance Compute) are driving demand for larger, faster deployments. They require significant contiguous space and power, influencing development priorities.
Market Trends
- Georgia Power is implementing stricter rules to curb speculative development and protect ratepayers. Developers must demonstrate end-user commitments, zoning confirmation and provide collateral for power procurement.
- Georgia Power has secured over 8 gigawatts (GW) of new generation capacity, scheduled to come online after 2030.
- Electric Membership Cooperatives (EMCs) are becoming increasingly competitive power providers, having recently secured contracts with both end-users and developers.
Notable Activity
- A major hyperscale user preleased over 300 MW and plans to secure an additional 600 MW by year-end.
- Stream Data Centers and Stack Infrastructure secured land use and zoning approvals in Douglas County, paving the way for significant capacity expansion.
Figure 1: Historical Market Information
Figure 2: Historical Supply and Demand
Figure 3: % of Total Primary Market Inventory
Figure 4: Market Fuel Mix
Figure 5: Average Asking Rates
Explore More Markets
- Local Response | Intelligent Investment
Charlotte-Raleigh Data Center Market
September 8, 2025 4 Minute Read
Data center and cell tower development in the Carolinas faces challenges due to Duke Energy's new power requirements.
- Local Response | Intelligent Investment
Dallas-Ft. Worth Data Center Market
September 8, 2025 4 Minute Read
Dallas-Ft. Worth data center market to double in size by 2026 with 89% of under-construction space preleased.
- Local Response | Intelligent Investment
Northern Virginia Data Center Market
September 8, 2025 4 Minute Read
Colocation vacancy rate rises to 0.72% in H1 2025. Limited availability drives expansion into emerging areas with rising rental rates.